TIA Interchange Project On Schedule

ADVERTISEMENT

Published: October 11, 2007

TAMPA - Construction on two highway projects at Tampa International Airport remains on schedule, airport and state highway officials said today.

Completion of the state's $205 million airport interchange project is scheduled for May 2010, but incentive plans have been created for the contractor that could result in the massive bridge and highway work just outside the airport's boundary to be ready for use by fall 2009.

The project includes a complete rebuilding of State Road 60 between Interstate 275 and the Veterans Expressway, including the area just west of the Grand Hyatt Tampa Bay hotel and the Spruce Street area west of West Shore Boulevard.

A separate $35.1 million project on airport property to widen the George Bean Parkway to and from the main terminal and improve how vehicles must merge for different airport locations is scheduled to be completed by October 2008.

In addition, travelers leaving Tampa International will be routed on some of the project's new road in December, including one across the tall bridge that is nearing completion.

Reporter Ted Jackovics can be reached at tjackovics@tampatrib.com or (813) 259-7817.

Share this:
Loading Comments...
Loading
Print This Print Bookmark and Share XML Feed For This Channel
 

ADVERTISEMENT

Advertisement

IYP and SEO vendors: SEO by eLocalListing | Advertiser profiles
Oops! Your email could not be sent because of the following errors: